COSASE Questions Delayed Works and Shs20 Billion Expenditure on Kyambogo AFCON Training Facility

Kyambogo University training ground facility

The Committee on Commissions, Statutory Authorities and State Enterprises (COSASE) has raised concerns over the progress and quality of works at the Kyambogo University training ground facility, questioning whether the project will be completed by the December deadline ahead of the Africa Cup of Nations (AFCON).

The concerns were raised by the committee chairperson, Muwada Nkunyingi, during a meeting with officials from the National Council of Sports (NCS), the Ministry of Works and Transport and the UPDF Engineering Brigade to assess the implementation of the project.

During the engagement, legislators questioned several discrepancies in the execution of the works, demanding explanations over the grading of different project phases, the positioning of the perimeter fence and the feasibility of installing a synthetic running track.

The MPs also questioned the proposed conversion of dressing rooms into laboratories, seeking clarification on whether the changes were consistent with the originally approved project designs and intended use of the facility.

Particular concern was raised over the reported payment of 100 per cent of the project cost, estimated at more than Shs20 billion, before all construction works had been completed.

The legislators demanded accountability from the implementing agencies, questioning how the funds had been utilised and whether the work delivered so far corresponds with the approved designs, specifications and contractual obligations.

They also sought assurances that the remaining works would be completed within the agreed timeframe to avoid compromising preparations for the continental football tournament.

However, the project implementers defended the progress, explaining that construction had been undertaken in phases depending on available funding and priorities agreed upon with the supervising engineers.

The officials maintained that the main playing pitch was ready for use, while outstanding works, including painting, installation of furniture and completion of dressing rooms, were expected to be finalised within the agreed timeframe.

The explanations did not entirely settle the legislators’ concerns, with the committee continuing to seek clarity on project execution, expenditure and adherence to approved specifications.

The Kyambogo facility is among the infrastructure projects intended to support Uganda’s preparations for hosting major continental football activities.

The committee’s scrutiny comes amid growing attention on the readiness of sports infrastructure, with Parliament seeking assurances that public funds allocated to the project will translate into quality facilities delivered within the stipulated timelines.

COSASE is expected to continue engaging the responsible agencies to establish the extent of outstanding works, financial accountability and whether the project will meet the December completion deadline.

By Francis Lubega

2nd Nov 2026

End

Share the Post:
Radio Sapientia
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.